Project Finish Date: Wed 8/29/07
Task Name | Start Date | Finish Date | % Complete |
---|---|---|---|
Implementasi Chaterina | Wed 8/8/07 | Wed 8/29/07 | 23% |
Data entry | Wed 8/8/07 | Wed 8/8/07 | 98% |
Outlet entry | Wed 8/8/07 | Wed 8/8/07 | 95% |
Kunjungan entry | Wed 8/8/07 | Wed 8/8/07 | 100% |
Data viewer | Wed 8/8/07 | Wed 8/8/07 | 95% |
Outlet viewer | Wed 8/8/07 | Wed 8/8/07 | 95% |
Kunjungan viewer | Wed 8/8/07 | Wed 8/8/07 | 95% |
Functionality test | Thu 8/9/07 | Thu 8/9/07 | 0% |
Report | Thu 8/9/07 | Mon 8/20/07 | 19% |
Outlet hit | Thu 8/9/07 | Thu 8/9/07 | 100% |
Kunjungan hit | Thu 8/9/07 | Thu 8/9/07 | 90% |
Price Summary | Fri 8/10/07 | Fri 8/10/07 | 100% |
Outlet by category | Fri 8/10/07 | Fri 8/10/07 | 75% |
Perbandingan harga | Mon 8/13/07 | Tue 8/14/07 | 0% |
Find Category | Wed 8/15/07 | Wed 8/15/07 | 0% |
Info pelayanan | Wed 8/15/07 | Wed 8/15/07 | 0% |
Report Jorney | Thu 8/16/07 | Thu 8/16/07 | 0% |
Journey plan | Thu 8/16/07 | Thu 8/16/07 | 0% |
Journey status | Thu 8/16/07 | Thu 8/16/07 | 0% |
Market share | Fri 8/17/07 | Mon 8/20/07 | 0% |
Starter pack | Fri 8/17/07 | Mon 8/20/07 | 0% |
Voucher fisik | Fri 8/17/07 | Mon 8/20/07 | 0% |
Vouher electronic buy | Fri 8/17/07 | Mon 8/20/07 | 0% |
Voucher electronic sell | Fri 8/17/07 | Mon 8/20/07 | 0% |
Perbandingan | Fri 8/17/07 | Mon 8/20/07 | 0% |
Functionality test | Tue 8/21/07 | Tue 8/21/07 | 0% |
Review | Wed 8/22/07 | Wed 8/22/07 | 0% |
Installation | Thu 8/23/07 | Sun 8/26/07 | 0% |
UAT | Mon 8/27/07 | Mon 8/27/07 | 0% |
Evaluation | Mon 8/27/07 | Tue 8/28/07 | 0% |
Project closing | Wed 8/29/07 | Wed 8/29/07 | 0% |